California EV Charger Rebate for Business: CALeVIP Fast Charger Incentives for PG&E, SCE and SDG&E Properties

The largest California EV charger rebate for business right now is the Fast Charge California Project (FCCP), run by CALeVIP for the California Energy Commission. The current window, FCCP-2, is open Oct. 7, 2026 through Jan. 14, 2027 with at least $28 million. It pays up to $55,000 per DC fast port at 150 to 274.99 kW and $100,000 per port at 275 kW and above, covering up to 100% of approved costs. A second window, FCCP-3, is planned for Feb. 24 to May 27, 2027 at $55,000 per 150 kW+ port.

There’s a catch most owners miss: only ready-to-build projects qualify, meaning you already hold an issued permit and a final utility service design. Hotels, charging hubs and business districts are no longer eligible site types. If you own a busy retail or mixed-use property in PG&E, SCE or SDG&E territory and don’t want to front that work, we install Level 3 fast chargers at $0 cost. Submit your California property for a free qualification check.

How much is the CALeVIP fast charger rebate?

CALeVIP pays a flat amount per charging port, based on guaranteed output, up to 100% of the project’s total approved costs.

WindowApplication dates150–274.99 kW per port275 kW+ per portFunding
FCCP-2Oct. 7, 2026 – Jan. 14, 2027 (5 p.m. PT)$55,000$100,000At least $28 million
FCCP-3Feb. 24 – May 27, 2027$55,000$55,000 (the 275 kW+ tier is dropped)Not yet published

Sources: CALeVIP FCCP-2, CALeVIP FCCP-3 and the California Energy Commission announcement. CALeVIP says the full FCCP-3 webpage will be released later, so treat those terms as preliminary.

Approved costs can include equipment, installation, planning and engineering. Once funds are reserved, you have 450 days to finish the installation and submit documentation. CALeVIP says it pays within 15 calendar days of approval.

Who qualifies for the California fast charger incentive?

Businesses, nonprofits and public agencies with a publicly accessible site anywhere in California can apply, if the project is ready to build. The FCCP-2 rules that decide most applications:

  • Ready-to-build: the application must include an issued permit and a final utility service design. CALeVIP says incomplete designs or permits make a project ineligible.
  • The applicant owns the chargers. The applicant must be part of the same entity as the incentive recipient and the charger owner. A property owner who leases space to a charging company isn’t the applicant. The charger owner is.
  • Site owner sign-off: the site owner, or someone with the owner’s permission on CALeVIP’s Site Verification Form, must authorize the project.
  • Site type: the site must be open to the public. Hotels, charging hubs and business districts are excluded.
  • Connectors: FCCP-2 requires at least 50% CCS connectors per site. FCCP-3 accepts J3400 and CCS, with at least one CCS connector per site.
  • Reliability and data: chargers must meet a 97% uptime standard. Networked chargers installed on or after Sept. 28, 2026 must report over OCPP 2.0.1 under California’s AB 2061 rules.
  • Queue: funding is reserved first-come, first-served. Ready-to-build projects in disadvantaged, low-income and tribal communities move to the top of the queue.

Can you stack CALeVIP with PG&E, SCE or SDG&E programs?

Mostly no. FCCP-2 funding “cannot be stacked/combined with other incentive funding.” That rules out other CEC money, investor-owned utility charger programs, municipal utility rebates, air district grants, community choice aggregator rebates and NEVI. If one address applies to both NEVI and FCCP, whichever processes first wins.

The allowed exceptions are the important ones:

  • Utility EV infrastructure tariffs (Rules 29 and 45), which fund the utility side of the meter.
  • Low Carbon Fuel Standard credit revenue.
  • Federal funding and tax credits, other than NEVI.

PG&E’s Electric Rule 29 shows how the utility-side piece works. PG&E designs and deploys the EV service extension from its distribution line to the service delivery point on the utility side of a separately metered charging site. That can include service conductors, poles, transformers, vaults, pads, conduit and trenching. To use it, you need proof of commitment to buy the chargers. You must activate them within 30 business days of energization, or up to 180 by agreement. You pay any extra cost if you want a route other than the shortest practical one. Distribution line extensions fall under a separate rule, Rule 15.

If your property is served by a municipal utility, such as LADWP in Los Angeles or SMUD in Sacramento, you can still apply for FCCP statewide. The investor-owned utility tariffs won’t apply, so check your utility’s own service rules.

Worked example: a 4 × 150 kW fast-charging site in Orange County

Take a 4-stall, 150 kW DC fast charging site at a grocery-anchored center in SCE territory, with an all-in budget of about $894,000 ($893,600 in our model). Our model includes about $93,560 of utility-side service work, or $23,390 per stall, for illustration. Actual Rule 29 scope depends on your utility’s design.

Line itemMathAmount
Project cost4 × 150 kW, all-in$893,600
CALeVIP FCCP-2 or FCCP-34 ports × $55,000$220,000
Utility-side service extension under the EV tariff (modeled)built by the utility instead of billed to youabout $93,560
Total supportabout $313,560 (35%)
Owner’s remaining costabout $580,000

If the same site used 275 kW+ chargers and got into FCCP-2 before Jan. 14, 2027, the CALeVIP piece would be 4 × $100,000 = $400,000. Hardware and electrical costs would rise too, though. CALeVIP also says projects can’t result in a profit for the applicant.

The bigger hurdle is timing. To be ready-to-build by Jan. 14, an owner starting today needs a design, a permit and a final utility service design within about 12 weeks. Miss that and you’re aiming for the Feb. 24 to May 27 window at the lower rate. Our Level 3 charging station installation cost guide breaks down the budget lines.

CALeVIP yourself vs. hosting chargers at $0

Because CALeVIP requires the applicant to own the chargers, a property owner has two real choices. You can become the charger owner and operator yourself, or host a charging company that owns the equipment and takes the program risk.

Apply for CALeVIP yourselfHost fast chargers with us
Upfront costFull project cost; incentive paid after install$0
Typical out-of-pocket (example above)about $580,000$0
Ready-to-build work (design, permit, utility design)You, before applyingWe handle utility coordination and permitting
Who owns and runs the chargersYou, with 97% uptime and AB 2061 reportingWe do, with a 99%+ uptime standard
Electricity and sales taxYouWe pay the power and handle sales tax
Repairs and damageYouWe do, including insurance coordination
How you earnCharging revenue minus costsGuaranteed stall rent or a profit share
TermOpen-ended ownership10 to 15 years
SpaceDepends on designAbout 5 spaces (4 stalls, expandable to 8)

If you want to be in the charging business, FCCP is one of the best incentives in the country. Most retail and mixed-use owners would rather collect rent than manage demand charges and reliability reports for a decade. That’s the deal we offer.

Which California properties fit hosted fast charging?

The best sites are busy, amenity-rich retail and mixed-use properties in dense, affluent suburban or urban trade areas. Think grocery-anchored and big-box centers and restaurant pads where drivers spend 20 to 30 minutes. In PG&E, SCE and SDG&E territory, strong markets include Orange County, the Inland Empire, San Jose and Fremont, Oakland and the East Bay, San Diego County, and Central Valley retail along I-5 and CA-99 in Fresno, Bakersfield and Stockton. Our sites average 10+ sessions per charger per day, or 40+ visits daily from a 4-charger site.

Check site fit with our EV charging station requirements guide and our explainer on EV charging land leases. For other states, see today’s guides to the Pacific Power EV charger rebate, the Georgia Power Make Ready program, the PSE&G EV charger rebate and PGE and ODOT rebates in Oregon.

How to apply for the Fast Charge California Project

  1. Confirm the site is publicly accessible and isn’t a hotel, charging hub or business district. Then use CALeVIP’s EV Charging Opportunity Finder to check need and priority-community status.
  2. Complete site design and get a final utility service design from PG&E, SCE, SDG&E or your municipal utility.
  3. Pull the building permit.
  4. Submit the application in the CALeVIP portal during an open window, with the site owner’s Site Verification Form. Choose eligible equipment and a network provider with a CALeVIP data sharing agreement.
  5. After funds are reserved, build within 450 days and submit final documentation.

Or hand us the whole list. Send us your California property address and parking count. We’ll screen it for traffic, nearby fast chargers, trade-area density and power availability. Qualified sites get a no-cost proposal and letter of intent.

Frequently asked questions

What is the best EV charger rebate for businesses in California?

For DC fast charging, it’s CALeVIP’s Fast Charge California Project. FCCP-2 pays up to $55,000 per 150 to 274.99 kW port and $100,000 per 275 kW+ port, up to 100% of approved costs, for applications filed Oct. 7, 2026 through Jan. 14, 2027. FCCP-3 is planned for Feb. 24 to May 27, 2027 at $55,000 per port.

What does ready-to-build mean for CALeVIP?

Your application must include an issued permit and a final utility service design. CALeVIP treats applications with an incomplete utility design or permit as ineligible for FCCP-2 funding.

Can a hotel get the California fast charger incentive?

Not through FCCP-2 or FCCP-3. CALeVIP says charging hubs, hotels and business districts are no longer eligible site types. Eligible sites must be available to the public.

Can I combine CALeVIP with PG&E, SCE or SDG&E incentives?

Generally no. FCCP funding can’t be stacked with utility charger programs, other CEC funding, air district grants or NEVI. The exceptions include the utility EV infrastructure tariffs (Rules 29 and 45) for utility-side work, LCFS credit revenue and non-NEVI federal funding.

Can I get EV chargers in California at no cost?

Yes. We fund 100% of equipment, installation, utility coordination and permitting for Level 3 fast chargers at qualified commercial properties. We own and maintain the station, pay for electricity, and pay you stall rent or a profit share over a 10 to 15 year term.