EV Charging for Mixed-Use Developments: How to Split Chargers Between Residents, Offices and Retail
EV charging for mixed-use developments works best when you split it by user, not by building. Residents and office tenants park for hours, so Level 2 chargers fit them. Retail and restaurant visitors stay 20 to 30 minutes, so Level 3 fast charging fits them. Federal station data backs this up. Among public charging sites tagged as shopping centers, 91% have DC fast charging. Among sites tagged as multifamily, just 1% do.
The split also changes who pays. Code-driven Level 2 for residents and tenants is usually an owner cost. Fast charging on the retail frontage doesn’t have to be. We fund, install and operate Level 3 fast chargers at $0 to the owner and pay monthly stall rent or a profit share. See if your mixed-use property qualifies for free EV chargers.
Why does a mixed-use property need two kinds of charging?
Because it has at least three kinds of drivers, and they park very differently:
| User | Typical parking pattern | Charger that fits | Who usually pays |
|---|---|---|---|
| Residents | Overnight, in assigned or garage spaces | Level 2 (or Level 1) | Owner or HOA, sometimes with resident fees |
| Office tenants and staff | Most of the workday | Level 2 | Owner or tenant |
| Retail, restaurant and gym visitors | Minutes to a couple of hours, all week | Level 3 DC fast | Can be $0 to the owner with a funded developer |
| Pass-through drivers | 20 to 30 minute top-ups | Level 3 DC fast | Same as above |
Put fast chargers in a resident garage and they sit idle overnight while residents hog them. Put only Level 2 on the retail side and visitors leave before they get much charge. Splitting by user avoids both mistakes.
What does the station data say about each use?
We counted every open public charging location in the U.S. Department of Energy’s Alternative Fuels Data Center by the facility type the station lists (developer.nlr.gov API, national pull of Nov. 3, 2026). Only about 21% of locations carry a facility tag, so read these as patterns, not a census:
| AFDC facility type | Public locations | With DC fast | Share with DC fast | Level 2 ports |
|---|---|---|---|---|
| Shopping center | 1,637 | 1,494 | 91% | 567 |
| Grocery | 439 | 348 | 79% | 206 |
| Restaurant | 550 | 346 | 63% | 516 |
| Hotel | 2,756 | 347 | 13% | 8,242 |
| Parking garage | 351 | 23 | 7% | 2,450 |
| Office building | 542 | 30 | 6% | 2,291 |
| Multifamily | 541 | 7 | 1% | 3,538 |
| All public locations | 83,779 | 15,922 | 19% | n/a |
The pattern is consistent. Where people stop briefly (retail, grocery, restaurants), operators build fast charging. Where people park for hours (homes, offices, garages), they build Level 2. A mixed-use site has both kinds of parking, so it should have both kinds of chargers.
How do building codes count EV spaces on a mixed-use site?
Rules vary by city, and many places have none for existing buildings. Two examples show how mixed-use gets handled.
**Charlotte’s development ordinance.** Charlotte’s UDO Article 19.3, in effect since June 2023, applies to multifamily stacked dwellings, residential components of mixed-use developments, hotels, and parking lots and structures. As summarized in the Electrification Coalition’s case study: 10 to 25 spaces need 20% EV-capable; 26 to 50 need 20% EV-capable plus one installed charger; above 50, it’s 20% EV-capable plus 2% installed.
**The 2024 IECC model (Appendix CG).** The model energy code’s optional commercial EV appendix, as summarized in the North Central Texas Council of Governments’ 2025 codes briefing, sets percentages by occupancy. For mercantile (Group M) and business (Group B) it’s 15% EVSE spaces and 30% EV-capable. For R-2 multifamily it’s 20% EVSE, 5% EV-ready and 75% EV-capable. When one shared garage serves several occupancies, the required spaces are split in proportion to each occupancy’s floor area. It only applies where a city or state adopts it.
Worked example: a 400-space mixed-use garage
Here’s how the counts could work for a hypothetical project. It’s illustrative only, so ask your plans examiner how your code actually applies.
| Assumption or result | Charlotte UDO (residential component) | 2024 IECC Appendix CG, if adopted as written |
|---|---|---|
| Spaces allocated to residential | 240 | 240 (60% of floor area), 200 units |
| Residential EV-capable | 48 (20% of 240) | 150 (75% of 200 units, the lesser of units or spaces) |
| Residential EV-ready | not required | 10 (5% of 200) |
| Residential installed chargers | 5 (2% of 240, rounded up) | 40 (20% of 200) |
| Spaces allocated to retail | 160 | 160 (40% of floor area) |
| Retail EV-capable | not covered by 19.3 unless it’s a principal-use parking lot | 48 (30% of 160) |
| Retail installed chargers | not covered by 19.3 unless it’s a principal-use parking lot | 24 (15% of 160) |
Two takeaways. First, the residential side is where code obligations pile up, and that’s Level 2 work the owner usually funds. Second, under stricter codes the retail side’s counts can be large too. If your jurisdiction lets fast chargers count toward installed-charger minimums, a hosted fast-charging site can carry part of that load at no cost to you. Ask early.
How should you lay out charging on a mixed-use site?
These rules of thumb come up again and again on mixed-use projects:
- **Fast chargers face the retail.** Put the 4 Level 3 stalls in surface parking by the shops and restaurants, visible from the main drive and open 24/7. Don’t put them inside a gated resident garage.
- **Level 2 goes where people sleep and work.** Resident and office chargers belong in garage levels or reserved areas, with access control if needed. See our guides to EV charging for apartments and EV charging for office buildings.
- **Keep the fast-charging service separate.** A fast-charging site typically needs its own utility service, transformer and switchgear pad. Keeping it off the building’s main service protects residential and office capacity.
- **Plan the equipment pad early.** Plan on about 5 spaces: 4 charging stalls plus a small equipment area. Our parking space guide shows typical layouts.
- **Write charging into the leases.** Retail and office leases may limit what the landlord can do in common parking areas. Check exclusive-use and parking clauses before you commit stalls.
Mixed-use property self-check
Your property is likely a strong candidate for hosted fast charging if:
- It has ground-floor retail, restaurants, a gym or a grocer that draws visitors seven days a week.
- There’s surface or open parking near the retail entrances, not only gated garage parking.
- You can give up about 5 spaces in a visible spot with 24/7 public access.
- There’s room for a transformer and switchgear pad nearby.
- It’s in a dense or affluent urban or suburban trade area.
- There’s no busy multi-stall fast-charging site a minute or two away.
If most of those fit, submit your property for a free qualification check. We screen nearby fast chargers, traffic, trade-area density and power availability. Qualified sites get a no-cost proposal and letter of intent.
What we cover on each side
**Retail side (Level 3, $0 to you).** We pay 100% of equipment, installation, utility coordination and permitting. We install Level 3 chargers delivering up to 500 kW, so most drivers are done in 20 to 30 minutes. We own, operate and maintain them with a 99%+ uptime standard, pay for the electricity, handle sales tax and repair damage. You choose monthly stall rent or a share of net charging revenue for a 10- to 15-year term. Our sites average about 10+ sessions per charger per day, and every session is 20 to 30 minutes of a driver near your tenants.
**Residential and office side (Level 2, owner-funded).** We also install Level 2 for residents, staff and tenants. It needs owner money, so it makes the most sense where utility or state incentives cover a large share of the cost. See our Level 2 EV charger installation guide, or for retail-led centers, our shopping center approach.
Frequently asked questions
What kind of EV chargers should a mixed-use development have?
Usually both. Level 2 fits residents and office tenants who park for hours. Level 3 DC fast charging fits retail and restaurant visitors who stay 20 to 30 minutes. Federal AFDC data shows 91% of public sites tagged as shopping centers have fast charging, vs. 1% of sites tagged as multifamily.
Do mixed-use developments have to install EV chargers?
It depends on your city. Charlotte’s UDO, for example, requires 20% EV-capable spaces plus 2% installed chargers for residential components of mixed-use projects with more than 50 spaces. Many cities have no rule for existing buildings. Check your local code.
How are EV spaces counted in a shared mixed-use garage?
Under the 2024 IECC’s optional Appendix CG, when one parking facility serves several occupancies, the required EV spaces are split in proportion to each occupancy’s floor area, then each share uses its own percentage. Only jurisdictions that adopt the appendix use this method.
Can a mixed-use property get fast EV chargers for free?
Yes, if it qualifies. We pay 100% of the cost of Level 3 fast chargers on the retail side, own and run them, and pay you stall rent or a profit share. Busy, amenity-rich mixed-use sites in dense areas are the best fit.
Where should fast chargers go on a mixed-use site?
In visible surface parking near retail entrances, open 24/7, not inside gated resident garages. Plan on about 5 spaces: 4 stalls plus a small equipment area, expandable to 8 stalls.
Will fast chargers take parking from residents or tenants?
Very little. A hosted site uses about 4 to 8 spaces, and idle fees start once a car finishes charging, so stalls turn over every 20 to 30 minutes instead of being used for all-day parking.