EV Charging Installation Companies: The 4 Types, Who Pays, and How to Pick One for a Commercial Property

EV charging installation companies fall into four types, and the biggest difference between them is who pays. An electrical contractor wires chargers you buy. A turnkey installer designs, permits and builds the whole project, but you still own it and pay for it. A charging network sells you hardware and software and partners with an installer. A funded developer, like us, pays for the entire Level 3 project, owns and runs it, and pays you monthly stall rent or a profit share.

If you want to own Level 2 chargers for guests or employees, hire a licensed contractor or turnkey installer. If you want DC fast charging on a busy commercial property without spending capital, talk to a funded developer first. Submit your property for a free qualification check and we’ll tell you which path fits your site.

What do EV charging installation companies actually do?

Every commercial charging project has the same steps, no matter who does them: a site assessment, a load study, electrical design, permits, utility coordination, trenching and concrete, equipment installation, commissioning, and then years of operations. The U.S. Department of Energy’s Alternative Fuels Data Center guide to developing charging infrastructure walks through the same planning, permitting and utility steps.

The real question is how many of those steps one company owns, and whether you or the company pays for them. That’s why two “installation companies” can quote you $0 and $900,000 for what looks like the same site.

The 4 types of EV charging installation companies

TypeWhat they doWho paysWho owns the chargersWho earns charging revenueBest for
Licensed electrical contractorWires and installs equipment you buy; pulls the electrical permitYouYouYouOwners who already picked hardware and a network
Turnkey installer (design-build)Site design, permits, utility work, construction, commissioning, sometimes maintenance plansYou (often with rebates)YouYouLevel 2 at hotels, offices and apartments where incentives cover most of the cost
Charging network or hardware sellerSells chargers and software subscriptions; refers or partners with installersYouYouYou, minus network feesOwners who want to set their own pricing and manage the program
Funded developer (owner-operator)Pays for, builds, owns, operates and maintains the stationThe developerThe developerThe developer, who pays you stall rent or a profit shareBusy commercial sites that want DC fast charging at $0

The first three are “you own it” models. The fourth flips the deal: the developer owns the equipment and the risk, and you get paid for the parking spaces. A 2023 report from the Eastern Transportation Coalition on contracting for public DC fast charging found that nearly all utilities, state agencies and automakers it interviewed wanted turnkey solutions with a single private company managing the whole site, from the site host agreement to installation, operations, maintenance and billing. One accountable party means fewer handoffs and less finger-pointing when something breaks.

Which type should a commercial property owner hire?

It depends on the charger type and who you want to own the risk.

For Level 2 (hotels, offices, apartments, workplaces)

Level 2 chargers are slower, so they suit places where cars park for hours. We install Level 2 too, but it requires owner money. It usually makes the most sense where utility or state incentives cover roughly 60 to 70% or more of the cost. For Level 2, a licensed contractor or turnkey installer is normally the right hire, and you’ll want one who has already completed projects under your utility’s rebate program. Our Level 2 EV charger installation guide covers the costs.

For Level 3 / DC fast charging (retail, restaurants, grocery, convenience)

DC fast charging is a different scale. In our model, a 4-stall, 150 kW site runs about $894,000 all-in for chargers, switchgear, transformer work and installation. Very few property owners want that on their balance sheet, plus the electricity bills, demand charges, software, repairs and 24/7 driver support that come after it.

That’s where a funded developer fits. We pay 100% of the project, including equipment, installation, utility coordination and permitting. We install Level 3 chargers up to 500 kW, and most EVs charge in about 20 to 30 minutes. You keep your parking lot and collect either guaranteed monthly stall rent or a fixed percentage of net charging revenue, with $0 invested. See what Level 3 installation costs if you want to compare against buying it yourself.

Owner-paid vs. developer-funded: a side-by-side for a 4-stall fast-charging site

QuestionYou hire an installer and own itA funded developer owns it
Upfront cost to youThe full project, about $894K in our 4 × 150 kW model, before incentives$0
Parking spaces usedAbout 5 (4 stalls plus equipment area)About 5 (4 stalls, expandable to 8)
Electricity and demand chargesYou payWe pay
Maintenance, repairs, damageYou pay or buy a service planWe handle it, with a 99%+ uptime standard
Sales tax on chargingYou collect and remitWe handle it
Your incomeCharging revenue minus all costsStall rent or profit share
TermEquipment life10 to 15 years

The owner-paid column can win if your site is a charging goldmine and you want to run an energy business. Most property owners would rather collect rent and keep their capital for the buildings they already own. We go deeper into this choice in our guide to EV charging station business models.

How to vet any EV charging installation company: a 10-point checklist

Use this list whether you’re hiring a contractor to install Level 2 or signing with a developer for fast charging.

  1. Electrical license: get the license number, class and state, and check it on your state board’s lookup.
  2. Named, certified electricians: ask which electricians will be on site and whether they hold EVITP certification. Federally funded (NEVI) projects require EVITP certification or a qualifying registered apprenticeship for electricians installing or maintaining chargers under 23 CFR 680.106(j). You can verify training through the Electric Vehicle Infrastructure Training Program.
  3. Utility experience: have they completed projects with your utility, and are they on its approved-contractor list if your make-ready or rebate program requires one?
  4. Load study first: a serious bidder checks your service capacity and transformer before quoting. A quote with no site visit is a red flag.
  5. Permit in their name: the company should pull permits in its own name and name the local authority.
  6. Commissioning and network activation: who tests the chargers, activates them on the network and sets pricing?
  7. Uptime commitment: federal rules for NEVI-funded stations require average annual uptime above 97% per port (23 CFR 680.116). Ask what uptime the company commits to and what happens if it misses.
  8. Damage and repairs: who pays when a car hits a charger, and how fast is it fixed?
  9. Who pays the power bill: get it in writing. With an owner-paid project, demand charges land on your meter.
  10. Contract terms: term length, removal at the end, assignment if you sell, and who restores the parking lot. Our EV charging host agreement guide lists the clauses to check.

For a deeper look at hiring a contractor specifically, see our commercial EV charger installer guide.

Red flags when comparing EV charging installation companies

  • A firm quote before anyone has looked at your electrical service or utility transformer.
  • “Free” offers that still leave you paying the electricity bill, the network subscription or repairs.
  • No answer on who maintains the equipment after year one.
  • A contract with no removal or site-restoration clause.
  • Revenue projections with no explanation of the utilization they assume.

What happens when you work with a funded developer?

With us, the process is short on your side. You submit your address and number of parking spaces. We screen the site for nearby fast chargers, traffic, trade-area density and power availability. Qualified sites get a no-cost proposal and letter of intent. Then come the lease, utility coordination, permitting and construction. Utility service upgrades usually take the longest, so timelines vary by site.

After go-live, we own, operate and maintain everything, including 24/7 monitoring, payment processing and driver support. We pay for the electricity and handle sales tax. Our sites average about 10 or more sessions per charger per day. If you want to see the site checks in more detail, read our EV charger site assessment guide.

The best sites are busy retail and mixed-use properties in dense suburban or urban areas, like grocery-anchored and big-box centers and restaurants, where drivers happily spend 20 to 30 minutes. Rural sites and thin trade areas generally don’t qualify. If that sounds like your property, see if your property qualifies for free EV chargers.

Frequently asked questions

What do EV charging installation companies charge?

It depends on the type. Electrical contractors and turnkey installers bill you for the project, which for DC fast charging can run close to $900,000 for a 4-stall, 150 kW site in our model. A funded developer like us charges $0 and pays you stall rent or a profit share instead.

Do I need a special license to install commercial EV chargers?

The work must be done by a licensed electrical contractor under a local permit. For federally funded NEVI projects, electricians must hold EVITP certification or have completed a qualifying registered apprenticeship program.

Is a free EV charger installation really free?

With us, yes for Level 3: we pay for equipment, installation, utility coordination and permitting, and we pay the electricity, maintenance and sales tax. Check any “free” offer for hidden costs like network fees or power bills on your meter.

Who owns the chargers after installation?

If you hire a contractor or turnkey installer, you own them. If a funded developer installs them, the developer owns, operates and maintains them for the 10 to 15 year agreement and pays you for the spaces.

Do you install Level 2 chargers too?

Yes. We install Level 2, for example at hotels, but Level 2 requires owner money. It usually makes sense where utility or state incentives cover roughly 60 to 70% or more of the cost.

How many parking spaces does a fast-charging installation need?

Plan on about 5 spaces: 4 charging stalls plus a small equipment area. Many sites start with 4 stalls and expand to 8 as demand grows.