Georgia Power EV Charger Installation for Businesses: Who Installs What, and the $0 Option (Augusta, Athens, Macon)
Georgia Power doesn’t install the EV charger itself. Through its Make Ready program, Georgia Power designs, installs, owns and maintains the electrical infrastructure behind the meter up to your charger, worth up to $300,000 per qualifying project, and you buy and install the charger. To qualify, the chargers must be public-facing, and you need at least six Level 2 ports or at least one DC fast charger. Georgia Power picks its own contractor for its part of the work. The program is scheduled to run through Dec. 31, 2028, or until funding runs out.
So a Georgia Power EV charger installation always has two crews and two budgets: the utility’s crew for panels, wire and conduit, and your crew for the chargers. If you’d rather not fund or manage either, we fund, install and operate Level 3 fast chargers at $0 to the property owner and pay you monthly stall rent or a profit share. See if your property qualifies for free EV chargers.
Who installs what in a Georgia Power EV charger installation?
Georgia Power’s Make Ready Program Criteria 2026-2028 spells out the split. Here’s how it divides between the utility, the property owner and a charging company, if you use one:
| Task | Georgia Power (Make Ready) | Property owner | Charging company (hosted model) |
|---|---|---|---|
| Site visit, power check and site design | Yes, and Georgia Power has final approval of the design | Joins the meetings | Joins the meetings and includes the owner |
| Panels, wire and conduit up to the charger | Designs, installs, owns and maintains | Grants an easement if required | Coordinates |
| Contractor for that infrastructure | Picks from its approved contractors | Can’t choose | Can’t choose |
| Buying, installing and energizing chargers | No | Pays, if self-funding | Pays and uses its own contractor |
| Bollards, signage, space striping | No | Pays, if self-funding | Pays |
| New service and metered account | Sets the meter | Applies, if self-funding | Applies |
| Utility-side upgrades | Standard line extension policy; may or may not be funded | May owe a contribution | Covers it in a hosted deal |
Two details trip owners up. First, Georgia Power says customers “do not get to choose their contractor” for the utility-owned work, so your electrician only handles the chargers. Second, Georgia Power will hold an easement on your property because it owns the equipment. If a charging company is the applicant, it must submit a letter from you approving the site and agreeing to grant that easement.
Does your site qualify for Make Ready?
According to Georgia Power’s Make Ready Infrastructure Program page, the program is open to Georgia Power business customers, including commercial and industrial sites, municipalities, universities, schools, hospitals and multifamily properties. Residential customers can’t use it.
The two core tests:
- Public-facing chargers. Chargers must be accessible to the public (or serve public fleets). Georgia Power’s criteria apply this segment by segment. Hotels and entertainment venues qualify only if the general public can reach the chargers. Guest-only or gated chargers don’t.
- Enough charging. You need six or more Level 2 ports, or at least one DC fast charger. Smaller or private projects get pointed to the Business EV Charger Plus Rebate instead.
Parts of the Augusta, Athens and Macon metros are served by electric membership corporations (EMCs), not Georgia Power. Check the name on your bill first. Make Ready only applies to Georgia Power accounts.
Six things that disqualify (or shrink) a Make Ready project
This checklist comes straight from the 2026-2028 criteria. Run your site through it before you get charger quotes:
- A legal mandate. Make Ready won’t pay for infrastructure that a city ordinance or legislation requires. Atlanta’s EV-ready rules for new construction are a good example; we cover them in our commercial EV charging Atlanta guide.
- It’s already in your general contractor’s scope. If charging infrastructure is already in your site plans and assigned to a GC and electrician, it isn’t eligible. You’d have to carve it out of the GC’s contract.
- Future-proofing. Extra conduit for chargers you might add later can’t be funded with Make Ready dollars.
- Parking deck wire runs. Georgia Power serves decks from the spot nearest the transformer. It won’t fund wire to individual spaces around the deck, and coring through the deck needs your structural engineer’s sign-off.
- Costs over the cap. Investment is capped at $300,000 per project unless otherwise authorized. You may owe a Contribution in Aid of Construction (CIAC) for anything above it.
- Customer-owned distribution. On campuses that own their own distribution system, the customer pays for upgrades to that system.
If you own several properties, Georgia Power works on up to five locations at a time, so apply for your best sites first.
How many chargers already serve Augusta, Athens and Macon?
We pulled open, public charging stations from the U.S. Department of Energy’s Alternative Fuels Data Center (AFDC) station API on Nov. 3, 2026, matched by city name in the station address. City-name matching undercounts suburbs, so treat these as rough counts:
| City | Public locations | Level 2 ports | DC fast ports | Sites with DC fast | Sites with 4+ fast ports | Hotel locations listed |
|---|---|---|---|---|---|---|
| Augusta | 40 | 66 | 72 | 11 | 7 | 3 |
| Athens | 34 | 58 | 54 | 11 | 6 | 2 |
| Macon | 29 | 46 | 37 | 10 | 5 | 4 |
| Columbus | 59 | 85 | 36 | 12 | 3 | 0 |
| Savannah | 65 | 161 | 29 | 11 | 2 | 7 |
Each of these cities has about a dozen or fewer fast-charging sites. Savannah has the most public locations but only two sites with four or more fast ports. For a busy retail, restaurant or travel-oriented property near I-20, I-75, I-16 or I-185, that’s a gap we look for. For more on these programs in Savannah, see our Georgia Power EV charging guide.
Make Ready vs. the Business EV Charger Plus Rebate
If you don’t meet Make Ready’s public-access or port-count rules, Georgia Power’s Business EV Charger Plus Rebate is the fallback. Here’s how the two compare, per Georgia Power’s pages on Nov. 4, 2026:
| Make Ready | Business EV Charger Plus Rebate | |
|---|---|---|
| What you get | Georgia Power builds and owns the infrastructure | A rebate check after installation |
| Value | Up to $300,000 per project | Up to $30,000 per project and $60,000 per year (businesses) |
| Rate | Not a per-kW rebate | $250/kW for Level 2, $150/kW for DC fast |
| Limit | Cap; CIAC may apply above it | 50% of total project cost |
| Who installs | Georgia Power’s contractor (infrastructure) plus yours (chargers) | Your licensed electrician does everything |
| Access | Public-facing only | Private, fleet and employee chargers OK |
| Timing | Through Dec. 31, 2028, or until funds run out | Chargers must be installed in the current calendar year |
Charger Plus pays after the fact. You’ll need paid invoices showing a $0 balance, site plans, spec sheets, a W-9 and photos. Pre-approval isn’t required, but Georgia Power recommends it. Multifamily properties get a separate tier of $5,000 per Level 2 charger, up to $50,000 per project. Our Georgia Power EV charger rebate guide walks through that application.
Worked example: an 8-port hotel Level 2 project in Augusta
Say a hotel off Washington Road or Riverwatch Parkway budgets $80,000 for 8 Level 2 ports, and the chargers are open to the public.
- Make Ready path: As in our earlier Georgia Power math, we assume about $24,800 of that budget is chargers, bollards and signage. That’s our planning assumption, not a Georgia Power number. If Georgia Power builds the rest, it covers up to about $55,200, or 69%. The hotel buys and installs the chargers.
- Charger Plus path: Georgia Power estimates $1,675 to $4,875 per Level 2 charger. Across 8 chargers, that’s $13,400 to $39,000, capped at $30,000. That covers 17% to 37.5% of $80,000.
We can install Level 2 too, and it’s at its best when incentives cover most of the cost, as Make Ready can for a public hotel lot. If you want to see whether your hotel clears that bar, submit your property here and we’ll check it. Our hotel EV charger installation guide covers the guest side.
Worked example: a 4-stall DC fast site in Macon
Now take four 150 kW DC fast chargers at a busy center off I-75, about $894,000 all-in.
| Line item | Owner-funded with Make Ready | Hosted by us |
|---|---|---|
| Project cost | $894,000 | $894,000, paid by us |
| Make Ready (up to) | $300,000 (34%) | Handled in our utility coordination |
| Owner’s remaining cost | About $594,000, plus any CIAC above the cap | $0 |
| Electricity, demand charges, networking | Owner | We pay |
| Repairs and damage | Owner | We handle |
| Owner income | Charging margin, if any | Monthly stall rent or profit share |
Make Ready makes owner-funded fast charging cheaper, but the owner still writes a large check and carries utilization risk. That’s why most Georgia owners we talk to prefer hosting.
How a hosted $0 fast-charging site works
Georgia Power’s criteria already allow charging companies to apply for Make Ready on a host’s property, with the owner’s approval letter. In our model:
- You pay $0. We fund the chargers, installation, utility coordination and permitting.
- You earn fixed monthly stall rent or a share of charging profit.
- We need about 5 parking spaces: 4 charging stalls, expandable to 8, plus an equipment area.
- We install Level 3 chargers up to 500 kW, and most sessions take 20 to 30 minutes.
- Terms run 10 to 15 years, with a 99%+ uptime standard.
- We pay the electricity, handle maintenance and damage, and manage sales tax on charging.
Our sites average 10+ sessions per charger per day, which brings drivers onto your property while they charge. Read how hosting works, or submit your Georgia property for a free fast-charger review.
Step-by-step: getting started
- Confirm you’re a Georgia Power business customer and have your account number.
- Decide whether you want public-facing chargers. Public access is what unlocks Make Ready.
- Run the six disqualifiers above, especially the mandate and GC-scope tests.
- Pick your path: self-funded Level 2 with Make Ready or Charger Plus, or hosted Level 3.
- If you’re self-funding, apply for pre-approval in Georgia Power’s portal before you sign charger contracts.
- If you want $0 fast charging, send us the site and we’ll screen power, traffic and nearby chargers.
Frequently asked questions
Does Georgia Power install EV chargers for businesses?
Not the charger itself. Through Make Ready, Georgia Power designs, installs, owns and maintains the electrical infrastructure up to the charger, worth up to $300,000 per qualifying project. You buy the charger and have your own contractor install and energize it.
Can I choose the contractor for Georgia Power’s Make Ready work?
No. Georgia Power assigns the contractor for the infrastructure it owns from its approved group. You can pick whoever you want to buy, install, energize and run the chargers.
What are the Make Ready eligibility rules?
You must be a Georgia Power business customer, the chargers must be public-facing, and you need six or more Level 2 ports or at least one DC fast charger. Installations required by a city ordinance or already in a general contractor’s scope aren’t eligible.
How much is the Georgia Power Business EV Charger Plus Rebate?
For businesses, $250 per kW for Level 2 and $150 per kW for DC fast, up to $30,000 per project and $60,000 per year, limited to 50% of total project cost. Chargers must be installed in the current calendar year.
Is Make Ready enough to make an owner-funded fast-charging site pencil out?
It helps, but on a four-stall, 150 kW site costing about $894,000, Make Ready’s $300,000 cap covers about 34%. The owner still funds roughly $594,000 and carries the operating costs and utilization risk.
Can I get fast chargers in Georgia Power territory at no cost?
Yes, if your property qualifies. We fund, install and operate Level 3 fast chargers at $0 to the owner, pay monthly stall rent or a profit share for 10 to 15 years, and handle electricity, maintenance and damage.