Georgia Power Make Ready Program: Free EV Charging Infrastructure for Hotels and Commercial Properties

The Georgia Power Make Ready program pays for the electrical infrastructure behind your meter, up to $300,000 per qualifying project. Georgia Power designs, installs, owns and maintains that equipment up to the charger: panels, wire, conduit and related work. You buy and install the chargers. A project qualifies if it’s public-facing and has at least six Level 2 ports or one DC fast charger. Georgia Power says the program is scheduled to run until Dec. 31, 2028, or until funding is used up.

For a Georgia hotel, that can take a big bite out of a Level 2 project. For a fast-charging site, it covers roughly a third of a typical 4-stall budget. There’s another way to use Make Ready that most owners miss: a charging company can apply on your property, with your approval letter. That’s how we install Level 3 fast chargers at $0 cost to qualified Georgia properties. Submit your property to see if it qualifies.

What does the Georgia Power Make Ready program cover?

Make Ready covers the behind-the-meter electrical work that gets power to the charger. That includes electrical panels, wires and conduit. Georgia Power uses its standard line extension policy to assess any utility-side upgrades, and those costs “may qualify” for Make Ready funding too, according to the 2026–2028 Make Ready program criteria.

What it doesn’t cover matters just as much:

  • The chargers. Georgia Power’s Make Ready page says it owns everything “up to but not including the charger.” You also cover bollards, signage and space painting.
  • Anything over $300,000. Above the cap, Georgia Power may charge you a Contribution in Aid of Construction (CIAC) for the difference.
  • Future proofing. Conduit or capacity for chargers you plan to add later can’t be paid with Make Ready dollars.
  • Mandated installs. Make Ready won’t fund infrastructure required by a city ordinance or legislation.
  • Work already in your plans. If the charging infrastructure is already in your site drawings and assigned to your general contractor, it isn’t eligible. It has to be carved out of the contract.

Does a hotel qualify for Georgia Power Make Ready?

Yes, if the chargers sit where the general public can use them. The criteria list Hospitality & Entertainment as eligible when chargers are “in an area that the general public may access.” Restricted-access chargers aren’t eligible. Guest-only charging behind a gate or in a key-card garage won’t qualify. Chargers must also be open to the general public at the same rate.

Hotels also need to plan around a few site rules:

  • Parking decks: Georgia Power serves the spot nearest the transformer and won’t run wire to individual spaces around the deck. Any coring through the deck needs a structural engineer’s sign-off.
  • Contractor: Georgia Power assigns one of its approved contractors for its infrastructure. You can’t choose that contractor, but you can hire anyone you like for the chargers.
  • Easement: Georgia Power may require one, and it will hold an easement for the equipment it owns on your property.
  • Multiple hotels: Georgia Power works up to five locations at a time for one customer, so rank your sites.

Also confirm your utility before you plan. Parts of metro Atlanta and much of rural Georgia are served by electric membership cooperatives or city utilities, not Georgia Power. Your electric bill will tell you.

Worked example 1: an 8-port Level 2 hotel project in Atlanta

Take an 8-port Level 2 project at a Midtown Atlanta or airport-area hotel budgeted at $80,000 all-in. Make Ready pays for the infrastructure, not the hardware, so the hotel’s share is the charger cost plus extras. For illustration, assume the chargers and extras come to $24,800 of the budget (our planning assumption, not a Georgia Power number). Your quotes will differ.

Line itemAmount
Total project budget$80,000
Hotel buys chargers, bollards, signage (assumed)$24,800
Make Ready infrastructure (Georgia Power builds and owns)up to $55,200
Share of project covered by Make Readyup to 69%
Hotel’s out-of-pocketabout $24,800

That 69% is an upper bound. It assumes Georgia Power’s design covers all non-hardware work. You’d still pay for power, networking, repairs and payment processing. Own a hotel? Submit your property and we’ll check whether incentives make Level 2 work or whether the site fits a $0 Level 3 host deal.

Compare the alternative. Georgia Power’s Business EV Charger Plus Rebate pays $250 per kW for Level 2 chargers, which Georgia Power estimates at $1,675 to $4,875 per charger. It’s capped at 50% of project cost and $30,000 per project, and chargers must be installed in the current calendar year. On an $80,000 hotel project, the rebate tops out at $30,000. Make Ready is usually worth more when you have six or more public ports. You can’t use both on the same project. Our Georgia Power EV charger rebate guide compares the two in detail.

Worked example 2: a 4 × 150 kW fast-charging site in Savannah

Now take a 4-stall, 150 kW DC fast charging site off I-95 or I-16 in Savannah, with an all-in budget of about $894,000 ($893,600 in our model).

Line itemAmount
Total project budget$893,600
Make Ready infrastructure capup to $300,000
Owner’s remaining cost (chargers, install, anything over the cap)about $593,600
Share coveredabout 34%

Fast-charging sites get one more Georgia Power benefit: the Charge It rider (CIEV-1). On a dedicated EV-charging meter, it cuts billed demand to 20% in year one, 40% in year two, 60% in year three and 80% in year four. The discount ends once the site’s rolling 12-month load factor reaches 15%. Demand charges are what sink many early fast-charging sites, so this is real relief. It still leaves the owner almost $600,000 in, plus a decade of operations.

Make Ready yourself vs. hosting chargers at $0

Georgia Power’s criteria include a section for EV charging provider companies. To get Make Ready funding on your property, the provider submits a letter from you, the site host, approving its operation on the premises and granting Georgia Power an easement. The charging company applies for the new metered service and picks its own contractor for the chargers. Georgia Power keeps final design approval and selects the contractor for its infrastructure. The provider must include you in conversations about the installation.

That’s the path we use. Here’s how the two routes compare.

You apply for Make ReadyWe host fast chargers
InfrastructureGeorgia Power, up to $300KGeorgia Power or us, at no cost to you
Chargers, installation, permittingYou payWe pay 100%
Typical out-of-pocket (examples above)about $25K (8-port L2) to about $594K (4-stall DC fast)$0
Electricity, demand charges, sales taxYouWe pay the power and handle sales tax
Maintenance, damage, uptimeYouWe do, 99%+ uptime standard
What you signApplication, easementSite host approval letter and easement, plus a 10 to 15 year agreement with us
How you earnCharging revenue minus costsGuaranteed stall rent or a profit share
Charger typeYour choiceLevel 3 DC fast, up to 500 kW

To be clear about fit: we install Level 2 too, but the owner pays for it, so it works best when incentives cover most of the cost, roughly 60 to 70% or more. If your goal is overnight guest charging, the Make Ready application is a good one to file. If your hotel or shopping center sits on a busy corridor where drivers will stop for 20 to 30 minutes, hosting Level 3 fast chargers costs you nothing and pays you monthly rent.

Which Georgia properties fit hosted fast charging?

We look for busy, amenity-rich sites in dense trade areas. That means grocery-anchored and big-box centers, restaurant pads and hotels near food and retail. In Georgia Power territory, good fits include in-town Atlanta (Buckhead, Midtown, Downtown), the airport corridor in College Park and Hapeville, Savannah’s I-95 and I-16 exits, Augusta’s Washington Road and I-20, and Athens near the Atlanta Highway retail corridor. You need about 5 spaces (4 charging stalls plus a small equipment pad), expandable to 8. Our sites average 10+ sessions per charger per day, so a 4-charger site brings 40+ visits daily.

For more on site fit, see our EV charging station requirements guide and how EV charging land leases work. If you also own property in Oregon, our Pacific Power EV charger rebate guide covers that state’s stackable rebates.

How to apply for Georgia Power Make Ready

  1. Gather the site’s Georgia Power account number, the site address and your contractor’s contact information, if you have one.
  2. Apply for pre-approval through Georgia Power’s online portal.
  3. Georgia Power reviews eligibility, then schedules a site visit to check power availability and design the service.
  4. Once the design is approved, you buy chargers while Georgia Power orders equipment. Georgia Power warns timelines vary with supply chain delays.
  5. After a pre-construction meeting, Georgia Power’s contractor builds the infrastructure, then your chargers go in.

Or let us do it. Submit your Georgia property address and parking count, and we’ll screen it for traffic, nearby fast chargers, trade-area density and power availability. Qualified sites get a no-cost proposal and letter of intent.

Frequently asked questions

How much does the Georgia Power Make Ready program pay?

Make Ready investments are capped at $300,000 per project unless Georgia Power authorizes more. Georgia Power designs, installs, owns and maintains the behind-the-meter infrastructure up to the charger. Costs above the cap may require a Contribution in Aid of Construction from the customer.

What are the Georgia Power Make Ready eligibility requirements?

The chargers must be public-facing, meaning accessible to the general public or serving public fleets. The project needs at least six Level 2 ports or at least one DC fast charger. Smaller projects can use the Business EV Charger Plus Rebate instead.

Can a hotel use Georgia Power Make Ready for guest EV charging?

Yes, if the chargers are in an area the general public can access at the same rate. Guest-only or restricted-access chargers aren’t eligible. Georgia Power also won’t run wire to individual parking deck spaces and assigns its own contractor for the infrastructure.

How long is the Georgia Power Make Ready program available?

Georgia Power says the program is scheduled to be available until Dec. 31, 2028, or until its funding threshold is met. Funding is limited, so earlier applications have the advantage.

Can a charging company use Make Ready on my property?

Yes. Georgia Power’s criteria let EV charging provider companies participate with a letter from the site host approving the operation and granting Georgia Power an easement. We use this path to build Level 3 fast chargers at $0 cost to qualified property owners.