ODOT Community Charging Rebates (Round 5): Up to $80,000 per Fast Charger Port for Oregon Businesses
ODOT’s Community Charging Rebates pay Oregon businesses up to $8,000 per Level 2 port or $80,000 per DC fast port, or 80% of eligible project costs (95% in ten reserved counties), whichever is lower, with a cap of $249,000 per site. Round 5 opened Oct. 1, 2026 with about $5.5 million, is the first round to fund DC fast charging, and runs first-come, first-served with no deadline until funds are reserved. Most of the money is set aside for DC fast projects, and 70% goes to priority (rural or low-income) communities.
It’s one of the richest state charger rebates in the country, but you still build, own and run the station. If you’d rather not, we install Level 3 fast chargers at $0 cost to qualified commercial properties and apply for incentives like this one as the equipment owner. Submit your Oregon property for a free qualification check.
How much funding is left in ODOT Round 5?
ODOT splits the money into buckets by charger type and location. These are the amounts on ODOT’s Community Charging Rebates page when we checked on Oct. 28, 2026.
| Charger type | Location | Funding available |
|---|---|---|
| Level 2 | Non-priority | $96,000 |
| Level 2 | Priority: Grant, Harney, Jefferson, Klamath, Lake, Morrow, Sherman, Union, Wallowa or Wheeler counties | $152,000 |
| Level 2 | Priority: remaining counties | $152,000 |
| DC fast | Non-priority | $960,000 |
| DC fast | Priority: the ten reserved counties | $1,760,000 |
| DC fast | Priority: remaining counties | $2,320,000 |
Three takeaways. Level 2 money is tight: the non-priority pool is enough for about 12 ports at the full $8,000. DC fast money is deeper, though ODOT’s Oct. 16 revision moved $560,000 from the non-priority DC fast bucket to the priority bucket based on the applications it was getting. And the ten reserved counties keep their set-aside only until Jan. 31, 2027, after which unclaimed funds go to priority projects statewide.
Whether your site is “priority” depends on its census block, not the city name. ODOT defines priority communities as rural or predominantly low-income, using EPA’s definition. Type your address into the Priority Type Locator map on ODOT’s page before you budget.
Who is eligible for ODOT Community Charging Rebates?
Businesses, nonprofits, public entities, Tribes and multifamily owners can apply, per ODOT’s Round 5 guidelines (revised Oct. 16, 2026). Businesses need a valid Oregon business license. The applicant must be the site owner or an authorized agent with a site verification form, site host agreement or land lease. Third parties can apply for you, but the rebate goes to whoever incurs the costs.
The site has to be one of three types:
- Publicly accessible parking: open to the public at least 60 hours a week and reasonably expected to draw visitors. Retail lots, destinations and paid lots count.
- Workplace: chargers for employees.
- Multifamily: at least 5 spaces serving 5 or more residences.
Hotels and motels count as publicly accessible if charging is open to the public. If a hotel limits charging to guests and staff, ODOT treats it as a workplace project. Fleet-only sites aren’t eligible.
What equipment and costs qualify?
Equipment rules
| Requirement | Level 2 | DC fast |
|---|---|---|
| Power | 9.6 kW or more | No minimum stated |
| Connectors | SAE J1772 or J3400 | CCS, J3400 or J3271 (MCS) |
| Certification | UL 2594 by an NRTL, plus ENERGY STAR | UL 2202 by an NRTL |
| Network | Networked for at least 5 years | Same |
| Maintenance | 5-year SLA or maintenance contract, paid in advance | Same |
| Ownership | New, purchased (not leased) | Same |
All installs must be done or supervised by EVITP-certified electricians (or an approved equivalent), under Oregon’s SB 582.
Eligible vs. ineligible costs
- Eligible: chargers, installation labor, electrical work and minor grid upgrades on your side, dedicated switchgear or battery storage, signage and striping, permits, lighting, ADA work, and up to 5 years of prepaid networking, maintenance and warranties.
- Not eligible: leased equipment, real estate, general building or parking construction, removing old chargers, overhead, electricity, upgrades to utility-owned infrastructure like substations, any cost covered by another incentive, and anything incurred before Oct. 1, 2026.
That last point is the stacking rule. ODOT subtracts other incentives from eligible costs before it applies its percentage, and you must apply for those other incentives first. ODOT can’t be combined with other federal grants, and chargers in a station funded by the federal NEVI program aren’t eligible. Our Oregon EV charger rebate guide shows the full Pacific Power plus ODOT stack for Bend and Medford.
Worked examples: Salem vs. Klamath Falls
Two sites, same budgets: an 8-port Level 2 hotel project at $80,000 and a 4-stall, 150 kW DC fast site at about $894,000, with all costs eligible. Salem (Marion County) gets the 80% cap. Klamath Falls (Klamath County) is one of the ten reserved counties and gets 95%. Salem is in PGE territory, where PGE’s business rebates are waitlisted, so we assume no utility rebate. Klamath Falls is served by Pacific Power, so we include its rebate first.
| Salem hotel, Level 2 | Klamath Falls hotel, Level 2 | Salem DC fast | Klamath Falls DC fast | |
|---|---|---|---|---|
| Project cost | $80,000 | $80,000 | $894,000 | $894,000 |
| Utility rebate | $0 | $28,000 (8 × $3,500) | $0 | $100,000 (site cap) |
| Eligible cost for ODOT | $80,000 | $52,000 | $894,000 | $794,000 |
| ODOT per-port limit | $64,000 | $64,000 | $320,000 | $320,000 |
| ODOT percentage limit | $64,000 (80%) | $49,400 (95%) | $715,200 (80%) | $754,300 (95%) |
| ODOT rebate after $249,000 site cap | $64,000 | $49,400 | $249,000 | $249,000 |
| Total incentives | $64,000 (80%) | $77,400 (97%) | $249,000 (28%) | $349,000 (39%) |
| Owner’s net cost | $16,000 | $2,600 | $645,000 | $545,000 |
Notice the pattern. For Level 2, ODOT plus a utility rebate can cover nearly everything. For DC fast, the $249,000 site cap binds long before the per-port or percentage limits, so a 4-stall fast site still leaves the owner with more than half a million dollars.
We install Level 2 too, and a hotel in a case like Klamath Falls is exactly where it makes sense, because incentives cover most of the cost. Send us your property to check which path fits.
How to apply, step by step
- Read the Round 5 guidelines and check your address on the Priority Type Locator map.
- Apply for your utility’s rebate first, if there is one.
- Complete the Site Verification and Recipient Acknowledgment Form.
- Submit the online application. You can reserve funds before installing, or apply after installation without a reservation (at your own risk if funds run out).
- Accept your reservation. You then have 270 days (Level 2 only) or 365 days (DC fast or mixed) to install and submit the post-installation application.
- Report charging data to ODOT for 5 years, starting six months after installation.
Need help? ODOT contracted Forth, a Portland nonprofit, for applicant support: ODOTchargingrebates@forthmobility.org or (503) 724-8670.
Where Oregon still needs fast charging
From the U.S. Department of Energy’s Alternative Fuels Data Center station data, pulled Oct. 28, 2026 (open, public stations by city address):
| City | Public locations | Level 2 ports | DC fast ports | Locations with DC fast |
|---|---|---|---|---|
| Portland | 262 | 591 | 135 | 33 |
| Salem | 127 | 207 | 51 | 17 |
| Eugene | 77 | 166 | 40 | 8 |
| Oregon statewide | 1,659 | 2,948 | 1,344 | n/a |
Eugene, home to the University of Oregon, has fast charging at just eight locations. That kind of gap is where a hosted fast-charging site on a busy retail property earns its keep.
Applying yourself vs. hosting with us
| Apply for ODOT yourself | Host Level 3 chargers with us | |
|---|---|---|
| Up-front cost (4 fast stalls) | About $545,000-$645,000 after rebates | $0 |
| Who owns the equipment and gets the rebate | You | We do |
| Prepaid 5-year network and maintenance | You buy it | We handle maintenance and damage |
| Electricity and sales tax | You | We do |
| 5 years of ODOT data reporting | You | We do |
| Your income | Charging revenue minus costs | Monthly stall rent or a profit share |
| Space and term | Your choice | About 5 spaces (4 stalls, expandable to 8), 10-15 years |
Our chargers deliver up to 500 kW, most sessions take 20 to 30 minutes, and our sites average 10+ sessions per charger per day with 99%+ uptime. If you own a busy, visible commercial property in Oregon, submit it for a no-cost qualification check.
Frequently asked questions
How much are ODOT Community Charging Rebates?
Up to $8,000 per Level 2 port or $80,000 per DC fast port, or 80% of eligible project costs (95% in Grant, Harney, Jefferson, Klamath, Lake, Morrow, Sherman, Union, Wallowa and Wheeler counties), whichever is lower. The maximum is $249,000 per site across Rounds 4 and 5.
Is ODOT Round 5 still open?
Yes. It opened Oct. 1, 2026 with about $5.5 million and has no deadline. Rebates are reserved first-come, first-served by funding bucket, and later applicants go on a waitlist funded by returned rebates.
Can ODOT rebates be combined with utility rebates?
Yes. You must apply for the utility incentive first and disclose it. ODOT subtracts other incentives from eligible costs before applying its percentage. ODOT rebates can’t be combined with other federal grants or NEVI-funded stations.
Do I have to install before applying?
No. You can reserve funds before installing, then finish within 270 days for Level 2 or 365 days for DC fast or mixed projects. You can also apply after installing, but funds aren’t guaranteed until reserved, and costs before Oct. 1, 2026 aren’t eligible.
Can a charging company apply for ODOT rebates on my property?
Yes. The rebate goes to the entity that incurs the costs, usually the equipment owner. When we host Level 3 chargers on your property at $0 cost, we’re the equipment owner and handle the application.