Oregon EV Charger Rebate for Bend and Medford Hotels and Businesses: Pacific Power + ODOT Math
The best Oregon EV charger rebate for businesses in Pacific Power territory is a stack: Pacific Power pays 75% of qualified costs up to $3,500 per Level 2 port or $30,000 per 150 kW+ DC fast port ($100,000 per site unless pre-approved), and ODOT’s Community Charging Rebates then pay up to $8,000 per Level 2 port or $80,000 per DC fast port, capped at 80% of the remaining eligible cost (95% in ten priority counties) and $249,000 per site. For a Bend or Medford hotel, that can cover close to 90% of a Level 2 project. For a 4-stall fast-charging site, it covers about 40%.
That’s still more than $500,000 for the owner on a fast-charging build. It’s why many Central and Southern Oregon owners host instead. We install Level 3 fast chargers at $0 cost to qualified commercial properties and pay you monthly stall rent or a profit share. Submit your Oregon property for a free qualification check.
How the Pacific Power and ODOT rebates work together
ODOT’s rebate is calculated after other incentives. Its Round 5 guidelines (revised Oct. 16, 2026) define eligible project costs as total costs minus ineligible costs and minus “other grants or incentives received.” You must apply for other incentives first, and tell both programs. So the order is: take Pacific Power’s rebate, subtract it, then apply ODOT’s percentage to what’s left.
| Pacific Power (Oregon) | ODOT Community Charging Rebates, Round 5 | |
|---|---|---|
| Level 2 | 75% of qualified costs, up to $3,500 per port | Up to $8,000 per port |
| Level 2, small business or multifamily | 100% of qualified costs, up to $4,500 per port | Same as above |
| DC fast | 75%, up to $15,000 per port under 150 kW or $30,000 at 150 kW+ | Up to $80,000 per port |
| Percentage cap | n/a | 80% of eligible costs (95% in Grant, Harney, Jefferson, Klamath, Lake, Morrow, Sherman, Union, Wallowa and Wheeler counties) |
| Site cap | $100,000 unless pre-approved | $249,000 per site across Rounds 4 and 5 |
| Timing | Apply within 12 months of purchase; final invoices required | First-come, first-served; no deadline until funds run out |
Pacific Power’s “small business” tier is worth checking for smaller hotels and motels. It applies to facilities under 20,000 square feet or with 20 or fewer employees at the charger location. Our Pacific Power EV charger rebate guide covers the utility side in more detail.
Worked example 1: an 8-port Level 2 hotel in Bend
Take an 8-port Level 2 project at a Bend hotel, budgeted at $80,000 all-in, with all costs eligible. Bend is in Deschutes County, so ODOT’s 80% cap applies.
| Step | Standard Pacific Power tier | Small-business tier |
|---|---|---|
| Project cost | $80,000 | $80,000 |
| Pacific Power rebate | 8 × $3,500 = $28,000 | 8 × $4,500 = $36,000 |
| Remaining eligible cost for ODOT | $52,000 | $44,000 |
| ODOT: lesser of 8 × $8,000 or 80% of remainder | $41,600 | $35,200 |
| Total rebates | $69,600 (87%) | $71,200 (89%) |
| Hotel’s net cost | $10,400 | $8,800 |
That’s one of the best Level 2 deals in the country, with real catches:
- Level 2 money is thin. ODOT says most of the $5.5 million Round 5 pot is reserved for DC fast. Its funding tracker showed $96,000 for non-priority Level 2 projects and $152,000 for priority ones. At $8,000 a port, the non-priority pool covers about 12 ports statewide.
- Equipment rules. ODOT requires Level 2 chargers rated 9.6 kW or more, networked for 5 years, with a 5-year maintenance agreement paid up front. Those prepaid costs are eligible, but they raise the budget.
- You build it. Pacific Power needs final invoices, so you pay first and get reimbursed.
We install Level 2 too, and this is the kind of case where it works: incentives cover most of the cost. Send us your hotel’s address to check eligibility. If your property is on US-97 or near the Old Mill District, hosted fast charging may earn you more, at $0 cost.
Worked example 2: a 4-stall DC fast site in Medford
Now four 150 kW DC fast chargers at about $894,000 all-in, at a retail site near I-5 in Medford (Jackson County, 80% cap).
| Step | Pacific Power at $100,000 site cap | If Pacific Power pre-approves more |
|---|---|---|
| Project cost | $894,000 | $894,000 |
| Pacific Power rebate | $100,000 (4 × $30,000 = $120,000, capped) | $120,000 |
| Remaining eligible cost | $794,000 | $774,000 |
| ODOT: lesser of 4 × $80,000, 80% of remainder, or $249,000 site cap | $249,000 | $249,000 |
| Total rebates | $349,000 (39%) | $369,000 (41%) |
| Owner’s net cost | $545,000 | $525,000 |
ODOT’s $249,000 site cap is the binding limit here, not the per-port amount. DC fast funding is deeper than Level 2: the tracker showed $960,000 for non-priority sites and $2.32 million for priority sites outside the ten reserved counties. ODOT gives reserved-fund projects 365 days from reservation to finish a DC fast or mixed project.
Where Oregon fast charging is still thin
We pulled the U.S. Department of Energy’s Alternative Fuels Data Center station data on Oct. 28, 2026, counting open, public stations by city address in Pacific Power cities.
| City | Public locations | Level 2 ports | DC fast ports | Locations with DC fast |
|---|---|---|---|---|
| Bend | 63 | 102 | 37 | 12 |
| Medford | 31 | 42 | 53 | 9 |
| Hood River | 19 | 30 | 32 | 4 |
| Corvallis | 31 | 62 | 5 | 2 |
| Albany | 13 | 16 | 8 | 5 |
| Oregon statewide | 1,659 | 2,948 | 1,344 | n/a |
Corvallis, home to Oregon State University, has fast charging at just two locations. Bend’s visitor traffic is spread across a dozen. For a busy retail center, grocery-anchored site or restaurant pad in these cities, that gap is the opportunity.
Applying yourself vs. hosting fast chargers with us
ODOT pays the rebate to the equipment owner, the entity that actually incurs the cost. When we host on your property, that’s us. You sign the site verification, and we take the application, the build and the risk.
| Apply for Pacific Power + ODOT yourself | Host Level 3 chargers with us | |
|---|---|---|
| Up-front cost (4 fast stalls) | About $525,000-$545,000 after rebates | $0 |
| Paperwork | Two applications, invoices, 5 years of ODOT data reporting | We handle it |
| Electricity and sales tax | You | We do |
| Maintenance, damage, uptime | You, with a prepaid 5-year contract | We do, with a 99%+ uptime standard |
| Your income | Charging revenue minus costs | Monthly stall rent or a profit share |
| Space | Your choice | About 5 spaces: 4 stalls, expandable to 8 |
| Term | Equipment life | 10-15 years |
Our chargers deliver up to 500 kW, most sessions take 20 to 30 minutes, and our sites average 10+ sessions per charger per day. Portland-area owners should read our PGE EV charger rebate guide, since PGE’s own rebates are waitlisted and ODOT is the main source there. Everywhere else in Oregon, submit your property and we’ll screen it for traffic, nearby chargers and power availability.
Frequently asked questions
What EV charger rebates are available in Oregon for businesses?
Utility rebates from Pacific Power (up to $3,500 per Level 2 port or $30,000 per 150 kW+ fast port) and PGE (currently waitlisted), plus ODOT’s Community Charging Rebates at up to $8,000 per Level 2 port or $80,000 per fast port, capped at 80-95% of eligible costs and $249,000 per site.
Can I stack Pacific Power and ODOT rebates?
Yes. ODOT allows combining with utility incentives, but you must apply for the other incentives first and disclose them. ODOT subtracts them from eligible costs before applying its 80% or 95% cap.
Is ODOT’s Community Charging Rebates Round 5 still open?
Yes. Round 5 opened Oct. 1, 2026 with about $5.5 million, has no deadline and runs first-come, first-served until funds are reserved. Later applicants go on a waitlist.
Do Oregon hotels qualify for ODOT rebates?
Yes. ODOT treats hotels and motels as publicly accessible sites if charging is open to the public. If a hotel restricts charging to guests and employees, ODOT classifies it as a workplace project.
Can I get fast chargers in Oregon at no cost?
Yes, by hosting. We install Level 3 fast chargers at $0 cost to qualified commercial properties, apply for the incentives as equipment owner, and pay you stall rent or a profit share over a 10-15 year agreement.